California High-Speed Rail Change Orders- Updated July 9, 2025
المشروع | رقم العقد | تغيير رقم الطلب | تاريخ الموافقة | مقاول | الفئة | لقب | المبلغ ($) | وصف | موافقة السلطة | طرف المقاول | دعم استشاري |
---|---|---|---|---|---|---|---|---|---|---|---|
CP 1 | HSR 13-06 | 00520 S1 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | اختلاف شروط الموقع | اختلاف ظروف الموقع - T&M | $522,000.00 | This is a Time and Material change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for additional costs to address the items identified within General Provisions Section 22.3 "Differing Site Conditions" in accordance with the Contract. To the extent Differing Site Conditions materially differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the Work, the Contractor or the Authority shall be entitled to an equitable adjustment in accordance with the Changes clause of the General Provisions. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 563 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | التغييرات في الخطط والمواصفات | Water and Sewer at Monterey St. (Between G St. and SR-41) - Construction | $11,522,917.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor and its Subcontractors for the costs to construct the new City of Fresno (COF) 16-inch water main, 30-inch sewer line and 44-inch sewer bypass at Monterey and G Streets in the COF. The scope includes all required connections, bypasses, removals and/or abandonments for this location as directed by, and/or as shown in the listed plan sheets in this Change Order. The cost incurred for performing the scope of work herein is a compensable expansion of the original Contract Scope of Work, resulting in an increase in the cost of performance. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 263.3 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | طرف ثالث ذو صلة | Sprint Costs due to UPRR CTC Project - Third Amendment Subtask 1.08B - 3rd Party Costs | $121,493.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide reimbursement as a not to exceed (NTE) to the Contractor for payments to be made to Sprint Communications Co. (Sprint), for costs incurred pursuant to Subtask 1.08 of the Authority's Master Utility Agreement with Sprint to relocate Sprint's facilities impacted by Union Pacific Rail Road's (UPRR) Centralized Traffic Control Project. Sprints facilities within UPRR Right of Way have to be relocated in the vicinity of Belmont and Weber Avenues within the City of Fresno. | إيان شودري - الرئيس التنفيذي | Robert Long - Project Manager/Director | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 603 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | طرف ثالث ذو صلة | Contractor Support for UPRR Performance of Track Work for CP-1 | $765,000.00 | This is a Time and Material change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for providing material, construction and traffic control support to Union Pacific Railroad and any other relevant Third Parties to not delay the Completion of "Project Work", as directed by the Authority in letter PCM-TPZP-08255 dated January 15, 2025. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 600 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | التغييرات في الخطط والمواصفات | DL-00243 Belmont Basin RR2 Interim Grading, Perimeter Wall, and Shoring - Design | $164,583.00 | This is a change to a contract for design services in the Central Valley. The reason for the change is to fully compensate the Contractor for design and engineering services to prepare an interim (temporary) grading plan and perimeter wall of the Fresno Metropolitan Flood Control District Belmont Basin RR2, along with incorporating revisions on the Belmont Basin Shoring of Excavation plans and report, as directed by the Authority Directive Letter DL-0243. | إيان شودري - الرئيس التنفيذي | Robert Long - Project Manager/Director | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 593 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | التغييرات في الخطط والمواصفات | DL-239 Permanent Wildlife Exclusion Fence Requirements - Design Costs | $47,300.00 | This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for engineering services cost incurred following the Authority's issuance of Directive Letter DL-0239, directing the Contractor to design, procure and install a Permanent Wildlife Fence attached to the Access Restricting Fence from Avenue 19 to north of the San Joaquin River, to address the Authority requirement and United States Fish and Wildlife Biological Opinion. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 588 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | طرف ثالث ذو صلة | Lumen Inspection Services | $140,000.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide reimbursement to the Contractor for payments to be made to Lumen Technologies (Lumen) for its Third Party costs to provide Inspectors for any non-Lumen utility relocation work within the Union Pacific Rail Road (UPRR) Right of Way, pursuant to a Subtask under the Authority's Master Utility Agreement with Lumen. The Inspectors will monitor utility relocation work to avoid damage to existing fiber optic facilities. This inspection services are in addition to the UPRR Project Inspector and Flagman as outlined in the published UPRR Wireline/Pipeline Encroachment Planning Guide and Construction Procedures. | إيان شودري - الرئيس التنفيذي | Robert Long - Project Manager/Director | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 579 | 5/7/2025 | المعلم بيريني / زاكري / بارسونز | التغييرات في الخطط والمواصفات | DL-242 Intrusion Protection Barrier (IPB) Maintenance Gates - Design | $44,476.00 | This is a change to a contract for design services in the Central Valley. The reason for the change is to compensate the Contractor for design and engineering services cost related to incorporation of Intrusion Protection Barrier maintenance gate layout per Authority Directive Letter DL-0242. Contractor is to revise Guideway Design Packages 2, 3 and 4, such that all pedestrian maintenance gates are in compliance with the directive. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 575 | 4/10/2025 | المعلم بيريني / زاكري / بارسونز | طرف ثالث ذو صلة | تقاطع مؤقت على شارع غولدن ستيت بوليفارد (GSB) - إنشاء | $3,000,000.00 | هذا تغيير في التوقيت والمواد لعقد خدمات إنشاءات في وادي سنترال فالي. ويهدف هذا التغيير إلى تعويض المقاول عن تكاليف التنفيذ الذاتي وتكاليف المقاولين من الباطن لإعادة ترتيب أعمال مشروع نورث غولدن ستيت بوليفارد (GSB) وفقًا لتوجيهات الهيئة وطلب مدينة فريسنو. يُطلب من المقاول استيعاب العمل حول نقل مرافق شركة PG&E الحالية، والسماح بتدفق حركة المرور في مسار واحد على الأقل في كل اتجاه ضمن مسارات مشروع نورث غولدن ستيت بوليفارد الجديدة، واستكمال مشروع نورث غولدن ستيت بوليفارد وفقًا للخطة المعتمدة بعد اكتمال نقل المرافق. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
CP 1 | HSR 13-06 | 605 | 4/10/2025 | المعلم بيريني / زاكري / بارسونز | التغييرات في الخطط والمواصفات | العمل في FMCD Shaw Avenue Storm Drain Shift Differential - T&M | $50,000.00 | هذا تغيير في التوقيت والمواد لعقد خدمات إنشاءات في وادي سنترال. يهدف هذا التغيير إلى تعويض المقاول ومقاوله الفرعي عن تكاليف الفرق بين أجور العمل المباشر وأجور العمل الإضافي، وذلك لتطبيق جدول عمل لمدة ستة (6) أيام في الأسبوع، وعشر (10) ساعات يوميًا، في منشأة تصريف مياه العواصف التابعة لدائرة مكافحة الفيضانات في فريسنو متروبوليتان في شارع شو، وذلك لإكمال أعمال تصريف مياه العواصف بحلول 1 مارس 2025. | إيان شودري - الرئيس التنفيذي | غسان عريقات - مدير مشروع / مدير | إريك ستاسيفيتش - مدير الإشراف في DB |
إظهار 1 إلى 10 من أصل 1,554 مُدخل
تبذل هيئة السكك الحديدية عالية السرعة في كاليفورنيا قصارى جهدها للتأكد من أن موقع الويب ومحتوياته تفي بمتطلبات ADA الإلزامية وفقًا لإرشادات الوصول إلى محتوى الويب 2.0 Level AA من ولاية كاليفورنيا. إذا كنت تبحث عن مستند معين غير موجود على موقع هيئة السكك الحديدية عالية السرعة في كاليفورنيا ، فيمكنك تقديم طلب للحصول على المستند بموجب قانون السجلات العامة من خلال صفحة قانون السجلات العامة. إذا كان لديك أي أسئلة حول الموقع أو محتوياته ، يرجى الاتصال بالهيئة على معلومات@hsr.ca.gov.