California High-Speed Rail Change Orders- Updated June 4, 2025
PROJECT | CONTRACT NO. | CHANGE ORDER NO. | APPROVED DATE | CONTRACTOR | CATEGORY | TITLE | AMOUNT ($) | DESCRIPTION | AUTHORITY APPROVER | CONTRACTOR COUNTERPARTY | CONSULTANT SUPPORT | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
CP 1 | HSR 13-06 | 575 | 4/10/2025 | Tutor Perini/Zachry/Parsons | Third-Party Related | Temporary Golden State Boulevard (GSB) Crossover - Construction | $3,000,000.00 | This is a Time and Material change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for self-performed and Subcontractors costs to implement re-sequencing of the work on North Golden State Boulevard (GSB) as directed by the Authority and requested by the City of Fresno. Contractor is directed to accommodate work around the existing PG&E utilities relocation, allow traffic flow in at least one lane on each direction in the new GSB lanes and to complete the North GSB per the approved plan after the utility relocation has been completed. | Ian Choudri - Chief Executive Officer | ||||||||
CP 1 | HSR 13-06 | 605 | 4/10/2025 | Tutor Perini/Zachry/Parsons | Changes to Plans and Specifications | Work at FMFCD Shaw Avenue Storm Drain Shift Differential - T&M | $50,000.00 | This is a Time and Material change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor and its Subcontractor for the costs of the difference between straight time and overtime wages for implementing a six (6) day per week, ten (10) hour per day work schedule at the Fresno Metropolitan Flood Control District Storm Drain (SD) installation at Shaw Avenue in order to complete the SD work by March 1, 2025. | Ian Choudri - Chief Executive Officer | ||||||||
CP 1 | HSR 13-06 | 607 | 4/21/2015 | Tutor Perini/Zachry/Parsons | Dispute Resolution | CP1 Design Impacts Settlement | $33,500,000.00 | This is a change to a contract for construction services in the Central Valley. This Change Order constitutes a settlement of ongoing disputes between the Contractor and the Authority related to the costs for design services to prepare CP-1 Third Party facility designs provided to Third Parties from Project award to 12/31/2026. The reason for the change is to capture the settlement and compensate the Contractor for costs of design services and impacts related to City of Fresno/Fresno Metropolitan Flood Control District (COF/FMFCD) Design Submittals, Railroad Facilities Design Submittals, and Work Plan/Crossing Applications (WP/CAs) through August 31, 2024, Engineering Support During Construction (ESDC) from Project Inception to 07/31/2023 and Time Related Design Overhead Cost from 02/02/2016 to 01/29/2018, | Ian Choudri - Chief Executive Officer | ||||||||
CP 1 | HSR 13-06 | 592 | 3/21/2025 | Tutor Perini/Zachry/Parsons | Third-Party Related | Additional Excavation required by City of Fresno for Belmont Water Line Abandonment - Cut and Cap Changes to the Water Line Tees | $117,486.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to compensate the Contractor for providing support to the City of Fresno (COF) in the removal of water line push-on tees at Belmont Avenue. During the process of performing the abandonment of the water line per the original Contract Scope of Work, COF decided they wanted the water line push-on tees removed. This request from COF is a change in the Contract Scope of Work as this required added excavation. A revised Traffic Control Plan is also required to accommodate access to these areas. | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager | ||||||
CP 1 | HSR 13-06 | 589 | 3/28/2025 | Tutor Perini/Zachry/Parsons | Changes to Plans and Specifications | Shift COF Utilities at Jensen Ave onto Authority Owned Parcels - Construction | $36,880,495.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to fully compensate the Contractor and its Subcontractors for the construction costs required to reconfigure the Jensen Avenue Sewer (SSI-087) and costs related to the Jensen Avenue Sewer Bypass (SSI-144). The differential in the costs of construction based on the original Contract designs and the costs of construction of the above listed items is an extension of the Contract scope of work causing an increase in construction costs that was not included in the Contractors original Scope of Work. | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Richard Feek - Project Controls/ Risk Manager | ||||||
CP 1 | HSR 13-06 | 00577 | 2/6/2025 | Tutor Perini/Zachry/Parsons | Third-Party Related | Comcast Temporary Relocation at Barstow Avenue Subtask 1.11 - 3rd Party Costs | $ 26,456.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide reimbursement to the Contractor for payments to be made to Comcast LLC for costs incurred to relocate Comcast's facilities impacted by construction of the new Golden State Boulevard (GSB). Comcast existing overhead lines along Barstow and San Madel Avenues are to be relocated to the new PG&E utility poles out of the new GSB alignment (Subtask 1.11). | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager | ||||||
CP 1 | HSR 13-06 | 00576 | 2/12/2025 | Tutor Perini/Zachry/Parsons | Third-Party Related | Level 3 Temporary Relocation at North Spur Subtask 1.09 - 3rd Party Costs | $ 137,597.00 | This is a change to a contract for construction services in the Central Valley. The reason for the supplemental change is to provide reimbursement to the Contractor for payments to be made to Level 3 Communications LLC for costs incurred to relocate Level 3 and Sprint facilities impacted by construction of the Fresno Trench Lid. Level 3 and Sprint facilities within the San Joaquin Valley Railroad North Spur are to be relocated in the vicinity of Thorne Avenue (Subtask 1.09) | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager | ||||||
CP 1 | HSR 13-06 | 00590 | 2/12/2025 | Tutor Perini/Zachry/Parsons | Changes to Plans & Specifications | E Central Avenue Overcrossing Changes - Constuction | $ 5,137,309.00 | This is a change to a contract for design and/or construction services in the Central Valley. The reason for the change is to fully compensate the Contractor and its Subcontractors for the costs to construct new work elements due to Authority directed changes to the original contract scope related to E Central Avenue Overcrossing between Cedar and Maple Avenues, crossing the High Speed Rail and Union Pacific Railroad trackways. | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager | ||||||
CP 1 | HSR 13-06 | 00551.01 | 1/27/2025 | Tutor Perini/Zachry/Parsons | Third Party Related | City of Fresno Sewer Main Collapse Settlement Monitoring | $ 90,000.00 | This is a change to a contract for construction services in the Central Valley. The reason for the change is to provide reimbursement to the Contractor for costs associated with the collapse of a 42-inch existing COF sewer main near the intersection of Weber and Brooks Avenues within the CP1 project limits. This supplemental Change Order is to provide for continued reimbursement of one-third (1/3) of the Settlement Monitoring costs incurred by the Contractor until the completion of the settlement monitoring activities in the area of the sewer collapse, anticipated to be completed in January 2025. This is a Time and Material Change order with the Not to exceed value of $90,000. | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager | ||||||
CP 1 | HSR 13-06 | 00236.02 | 12/31/2024 | Tutor Perini/Zachry/Parsons | Third-Party Related | City of Fresno Fees | $ 4,500,000.00 | This is a change to a contract for design services in the Central Valley. The reason for the supplemental change is to reimburse the Contractor for payments to be made to City of Fresno (COF) for CP-1 design plan reviews, oversight, audit, construction inspection and support services related to the Project which require COF approval or review. | Ian Choudri - Chief Executive Officer | Ghassan Ariqat - Project Manager/Director | Eric Stassevitch - DB Oversight Manager |
Showing 1 to 10 of 1,546 entries
The California High-Speed Rail Authority makes every effort to ensure the website and its contents meet mandated ADA requirements as per the California State mandated Web Content Accessibility Guidelines 2.0 Level AA standard. If you are looking for a particular document not located on the California High-Speed Rail Authority website, you may make a request for the document under the Public Records Act through the Public Records Act page. If you have any questions about the website or its contents, please contact the Authority at info@hsr.ca.gov.