CEO Report
October 9, 2025
Vision | One Year Later: Accomplishments and Looking to the Future | Related Materials
A VISION FOR DELIVERING HIGH-SPEED RAIL IN CALIFORNIA
- Gilroy to Palmdale Corridor
- Connecting the Bay Area, the Central Valley, & Southern California
- Integrated Statewide System
- Linking with Caltrain, Metrolink & Brightline West
- Early Monetization & Commercialization
- Leverage assets for energy, broadband, data centers, express parcel services, etc.
- Sustainable Future
- Advancing California’s climate, mobility, housing, & economic goals
ONE YEAR LATER: ACCOMPLISHMENTS & LOOK AHEAD
Incorporating lessons learned & charting a clear path forward for continued success
- Accomplishments
- Funding & Financing
- Secured cap-and-invest funding – $1 billion annual through 2045 – largest in program history
- Developed most expansive ancillary revenue strategy framework (clean energy, broadband, etc.)
- Conducted bottoms-up cost estimate and schedule reviews
- Right-sized current consulting contracts – achieving $80 million in savings through efficiency
- Procurement Strategy
- Renewed partnerships with private sector
- January Industry Forum: +100 private sector firms represented
- Released request for expressions of interest for Public Private Partnership (P3): 30 responses
- Cap-and-invest commitment secured
- Implemented new approach to reduce service costs
- Multiple Award Task Order Contract (MATOC)
- Materials Procurement
- P3/Private Partnerships
- AEIDIQ
- Renewed partnerships with private sector
- Design & Construction
- Completed cost-optimization work by updating the Design Criteria manual
- Construction Package 4 substantially complete
- Completed first phase of railhead construction, track and signal installation
- IT advancements in early works, engineering and contract management
- Organizational Structure
- New executive team
- Authority reorganization for operational efficiency – run like a business
- Right-sized current consulting contracts to be consistent with strategic priorities
- Added key performance indicators to three construction management firms and other consultant contracts across the board
- Internal IT advancements to support program delivery
- Balancing Risk
- Executed procurement, project delivery, administrative and funding actions for managing current & potential risks
- Conducted annual Enterprise Risk Assessment
- Legislative Action
- Passed legislation providing CEQA exemptions for stations & facilities
- Senate Bill 131
- Developed forward-thinking legislative concepts to streamline delivery:
- CEQA Exemption for Clean Power Facilities
- Utility Relocation Streamlining/Third-Party Management
- Prioritized System for right-of-way court cases
- Sales Tax Exemption on Purchasing Materials
- Encroachment Permitting Authority
- Bonding Provisions
- Boosting Land Use Authority and Value Capture Mechanisms
- Additional Funding
- Discussions with Department of Fish and Wildlife to expedite permitting process
- Passed legislation providing CEQA exemptions for stations & facilities
- Funding & Financing
- Looking to the Future
- Funding & Financing
- Continue to broaden funding sources beyond Cap-and-Invest
- Continue wholistic cost estimates and schedule modifications
- Adopt creative financing solutions
- Apply early commercialization approach
- Procurement Strategy
- Implement lessons learned from the private sector from Request for Expressions of Interest
- Secure P3/Private Partnerships to Accelerate Delivery
- Release and award MATOC contracts/AEIDIQ
- Finalize Contracts & Long Lead Commodities Purchases and Deliveries
- Deliver Procurement Strategies
- Track, OCS and Systems
- Trainsets
- Project Delivery Partner
- Clean Energy P3
- Track & Systems Construction Contract (TSCC)
- Anticipate Board consideration in November for a December release to market.
- Work covers construction, installation, testing, and commissioning of track, overhead catenary system (OCS), traction power, train control, telecommunications, and SCADA
- systems.
- The RFP will include:
- Lead contractor for track and OCS;
- Designer for traction power, train control, telecommunications, and SCADA systems; and
- Integrator responsible for testing and commissioning.
- Detailed pricing for the track and OCS construction work.
- The RFP will not include:
- Designer for track and OCS (Authority-retained);
- Power generation and battery electric storage systems (separate power generation procurement); or
- Equipment manufacturer of traction power, train control, communication systems.
- The TSCC will undertake solicitation of these OEMs/vendors post-award on an open book basis, within an Authority-allocated allowance, following further advance of the design work.
- Design & Construction
- Pursue additional cost optimizations
- Finish railhead civil construction facilities
- Enact legislative reforms to streamline processes for critical conditions
- Complete Central Valley civil works
- Lay track by 2026
- Environmentally clear entire route from San Francisco to Anaheim by 2026
- Develop and implement innovative technological systems to support construction
- Organizational Structure
- Continued organizational structure refinements
- Continue to build and enhance key executive leadership
- Enhance in-house expertise with less reliance on consultants
- Advancing technological systems to support operations
- Continue Development Implementation of IT Systems to Support Operations & Delivery
- Develop key performance indicators for design firms
- Balancing Risk
- Strengthening risk management framework to drive schedule optimization
- Identify and mitigate risks to:
- Right-of-way
- Third-party utilities
- Environmental clearance
- Other issues as identified
- Legislative Action
- Advance Legislative initiatives around bond provisions/non-impairment language
- Continue to pursue Legislative priorities
- Funding & Financing
RELATED MATERIALS
Organizational Chart
View the latest organizational chart
Contact
Board of Directors Secretary
(916) 324-1541
boardmembers@hsr.ca.gov
The California High-Speed Rail Authority makes every effort to ensure the website and its contents meet mandated ADA requirements as per the California State mandated Web Content Accessibility Guidelines 2.0 Level AA standard. If you are looking for a particular document not located on the California High-Speed Rail Authority website, you may make a request for the document under the Public Records Act through the Public Records Act page. If you have any questions about the website or its contents, please contact the Authority at info@hsr.ca.gov.